Issue details

KD 4759 - Meridian Water Phase 1 - Authority to Procure a Remediation Contractor

A new remediation contractor is required to complete the remediation of Meridian Water Phase 1 following the previous contractor Hydrock going into administration in March 2018. A number of options have been explored and restricted procure is the preferred option.

Decision type: Key

Reason Key: Expenditure > £250,000;

Decision status: For Determination

Wards affected: (All Wards);

Notice of proposed decision first published: 19/09/2018

Decision due: Not before 21st Oct 2018 by Sarah Cary (Executive Director Place)

Department: Place

Contact: Chisholm Hardy, Senior Project Manager chisholm.hardy Email: @enfield.gov.uk Tel: 0208 379 6769.

Part 1 & 2 (Para 3): Part 1 & Part 2 (Para 3)