Council entered into the GDA in October 2020.
Variation are required to the GDA to 1.) contractually de-link Rail
Works; and
2.) Increase Preliminary Funding by £7.6M to allow the Rail
PCSA to be instructed and critical works on Street Works to
continue.
Decision type: Key
Reason Key: Expenditure/Savings > £500,000;
Decision status: Recommendations Approved
Wards affected: Upper Edmonton;
Notice of proposed decision first published: 27/05/2022
Decision due: 30 Jun 2022 by Leader of the Council
Department: Housing Regeneration and Development
Contact: Pauline Albers, Regeneration Officer Email: pauline.albers@enfield.gov.uk Tel: 0208 379 5511.
Part 1/2 (Para x): Part 1 & 2 (Para 3)