Issue - meetings

KD 4864 - Meridian Water – Meridian One Developer Procurement

Meeting: 24/04/2019 - Cabinet (Item 6)

6 Meridian Water – Meridian One Developer Procurement pdf icon PDF 602 KB

A report from the Executive Director – Place is attached. (Report No.216, agenda part two also refers) (Key decision – reference number 4864)

(Report No.213)

(7.40 – 7.50 pm)

 

Additional documents:

Minutes:

Councillor Nesil Caliskan (Leader of the Council) introduced the report of the Executive Director – Place (No.213) seeking approval to enter into a development agreement with the highest scoring bidder to develop the site in accordance with the terms of the procurement.

 

NOTED

 

1.            That Report No.216 also referred as detailed in Minute No.15 below.

 

2.            The background to the proposals as outlined in the report. In July 2018 the Cabinet had agreed to bring forward three early sites from the Meridian Water project for development. The first of these three sites was Phase 1 at Willoughby Lane which already had the benefit of an outline planning consent for 725 residential units.

 

3.            That Cabinet had agreed to the procurement of developers to deliver Meridian One using the London Development Panel. The report detailed the procurement processes followed and the results of the evaluation. The report recommended that the Council enter into a Development Agreement with the highest scoring bidder to develop the site in accordance with the terms of the procurement. The specific requirements that had been required by the Council as part of the procurement process were noted.

 

4.            The community engagement events in the local area that had been held to date and, those to take place in the future.

 

5.            The further required discussions and negotiations that would take place with the chosen developer, as outlined in the report.

 

6.            In response to questions raised, the volume and timing of the provision of affordable housing as part of this phase of the development was discussed and explained to Members in detail. This included the provision of affordable rented units.

 

7.            Councillor Caliskan (Leader of the Council) expressed her thanks and appreciation to colleagues and officers for the significant amount of work that had been undertaken over the last 12 months, and previously. The current administration had been very clear on its priorities and vision for the Meridian Water development and had been pleased with the interest received from potential developers.

 

Alternative Options Considered: NOTED, the detailed alternative options that had been considered as set out in section 4 of the report including: end current procurement and re-procure; end current procurement and the Council self-deliver; and, end current procurement and sell land.

 

DECISION: The Cabinet agreed to

 

1.            Approve the selection of Bidder A as the Preferred Developer and authorise the Programme Director – Meridian Water (In consultation with the Director of Law and Governance and the Director of Finance) to enter into a Development Agreement and ancillary documents for Meridian One.

 

2.            Prior to signing the Development Agreement authorise the Executive Director – Place (in consultation with the Director of Law and Governance and Director of Finance) as far as was permitted to enter into discussions with Bidder A to secure up to 50% affordable housing with the Council retaining at least 75 affordable rented units on the site.

 

3.            That at the conclusion of the discussions referred to above, authority be delegated to the Leader  ...  view the full minutes text for item 6