Report will seek approval to start the
procurement process to select a contractor to build the strategic
non-rail infrastructure in Meridian Water.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Wards affected: Upper Edmonton;
Notice of proposed decision first published: 31/10/2018
Decision due: Not before 28th Nov 2018 by Relevant Cabinet Member or Director
Department: Place Department
Contact: Pauline Albers, Regeneration Officer Email: pauline.albers@enfield.gov.uk Tel: 0208 379 5511.
Consultees
Director of Law and Governance
Part 1 & 2 (Para 3): Part 1 & 2 (Para 3)