Issue details
* KD 2099 Authority for the Comprehensive Development Initiative (CDI) Phase 1 to proceed, in accordance with Cabinet report dated 5 April 2006.
Decision type: Key
Reason Key: Significant Impact on 2 or more Wards;
Decision status: Recommendations Approved
Wards affected: Edmonton Green; Enfield Highway; Enfield Lock; Highlands; Jubilee; Lower Edmonton; Southgate Green; Turkey Street; Upper Edmonton;
Decision due: Not before 2nd Jun 2008 by Cabinet Member for Social Housing
Department: Resources Department
Contact: Sarah Carter, Head of Development & Estate Renewal Email: sarah.carter@enfield.gov.uk Tel: 020 8379 4260.
Part 1 & 2 (Para 3): Part 1
Documents
- Cabinet Report No 193, 24.11.04 : Report back on CDI Phase 1 consultation
- Delegated decision 12.3.04: CDI Phase 1 - Award of preferred bidder status
- Cabinet Report No 155, 5.11.03: Disposal of CDI Phase 1 Sites
- Cabinet Report No 331, 26.4.06: Update on progress on CDI Phase 1